The Federal Government has issued a warning to potentially cancel the contracts of Julius Berger and CCECC pertaining to the Calabar Itu Road project.
Minister of Works, David Umahi has requested the prompt reactivation of the two construction companies to their respective project sites within one week, failing which their contracts may be subject to termination.
During a Stakeholders’ Engagement in Uyo on Saturday, Umahi directed the contractors to immediately mobilize to the project site, noting that sufficient funds for the Lagos-Calabar Coastal Highway projects have been provided by President Bola Ahmed Tinubu.
He said, “We use this opportunity to warn CCECC, out of 35 kilometres, they just completed 2.5 kilometres double carriage way and 4.5 on single; that is very terrible. You talk to them, they say it is because of compensation
“Our dear governor (Pastor Umo Eno) has since settled the compensation issue, so we have given them a marching order to mobilise to at least three sections of the road. Mr President has given enough money to fund the project; the same thing with Julius Berger.
“By the end of this coming week, if Julius Berger fails to remobilise to site, and CCECC fails to get mobilised in at least three sections, the jobs will be terminated.
“The worst of the roads in the entire South-South remains this Akwa Ibom to Cross River through Itu and Udoakpan Ekpo, and also the section that is being done by RCC.
“RCC has collected over N40 billion on that road, 15 kilometres of road, N156 billion inherited from the past administration, we have kept the price even though we don’t believe in it, but since it has been awarded and signed; but they are playing tricks.
“We have been on them to change their minds but by the end of next week, our 14 days notice of termination will elapse and we would terminate the project and give it to those who have mastery in the laying of concrete to come and use concrete in doing those roads.”
Source: X/Imranmudhz