Reps Query Chevron Over $7.8 Billion Increase in Cost of Gas-to-liquids Project

0 259
CBN

An ad hoc committee of the House of Representatives has queried Chevron Nigeria Limited over the implementation of the Escravos gas-to-liquids (EGTL) gas project, which should cost $2.9 billion, but was quoted as $10.7 billion.

The committee on the Joint Venture of the NNPC limited raised concerns when the management of Chevron appeared before the lawmakers in Abuja.

CBN

The committee chairman, Hassan Fulata (APC-Jigawa), demanded an explanation and the reasons behind the review of the project’s cost from $2.9 billion to $10.7 billion, a $7.8 billion increase.

Mr Fulata said a similar project was executed in Qatar for less than $2.5 billion within a very short period, adding that NNPC should have protested the cost review and demanded a value-for-money audit.

Responding, Chevron’s director of joint venture, Monday Ovuede, told the committee that several factors caused the upward review of the project’s cost from the initial $2.9 billion to $10.7 billion.

Mr Ovuede explained that immediately after the project was signed, prices of commodities like oil and steel went up, necessitating an upward review of the project.

He added that Chevron agreed to a value-for-money audit despite not having it in the contract for the project.

“This is a very complex technology to be executed in this part of the world. When project construction started in 2005— coincidentally, if you check the record, commodity prices, including oil and steel, started rising in the international market.

“The project was given as engineering, procurement and logistics, which means the sum was fixed. In the course of executing the contract, the contractors came back,” he said.

On the Qatar project, Mr Ovuede explained that the project was built in an industrial complex with a seaport and access to an international airbase.

According to him, there was access to skilled labours compared to Nigeria, but such skills were hard to acquire.

“The plant in Qatar is built in an industrial complex close to a seaport, and there is an international airbase there.

“It has access to skilled labour from Europe, when you come to our side, we try to build—for some of the technology, we had to develop the local labour to the level required to implement the project,” he said.

Despite the explanations, the legislators remained dissatisfied and requested documents to back the claims.

Ibrahim Isiaka (APC-Ogun) moved a motion for Chevron to submit a written response justifying the increment.

In his ruling, Mr Fulata alleged that Chevron was claiming capital allowance for the project without capital importation or a certificate to make such a claim.

He ruled Chevron should appear again on Tuesday, October 11, with relevant documents to defend its claims.

(NAN)

0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x